Construction of 6 Blocks of Block Nos.1, 2, 3, 4, 5, 6 - Type–A:…
Construction of 6 Blocks of Block Nos.1, 2, 3, 4, 5, 6 - Type–A:… is registered with TNRERA as TN/14/Building/0037/2021 (Building registration, 2021). The promoter is THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board, Cuddalore Division, who has 11 projects on the TNRERA register. The RERA-committed completion date is 1 Dec 2023 — that date has now passed. Committed dates are legally binding under RERA.
About this registration
Construction of 6 Blocks of Block Nos.1, 2, 3, 4, 5, 6 - Type–A: Ground Floor + 2 Floors with 24 tenements in each Block and by totalling 144 tenements. 4 Blocks of Block Nos.7, 8, 9, 10 - Type–B: Ground Floor + 2 Floors with 48 tenements in each Block and by totalling 192 tenements. 3 Blocks of Block Nos.11, 12, 13 - Type–C: Ground Floor + 2 Floors with 60 tenements in each Block and by totalling 180 tenements and by totalling altogether 516 tenements comprised in S.Nos.1082/2 & 1083/1 of Kailavanampettai Village, Vedaranyam Taluk, Nagapattinam & Myladuthurai District.
Approval: Technical Sanction accorded by the Deputy Director, O/o. District Town & Country Planning, Nagapattinam District vide Letter No. 55/2020/ND-2, dated 12.11.2020 and the Building Permission issued by the Commissioner, Veda
Status on register: Progress of Work as on June 2021
Builder track record: THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board, Cudd
THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board, Cuddalore Division has 11 projects on the TNRERA register since 2020, with no completion-date extensions on record. See the full record →
Frequently asked
Is Construction of 6 Blocks of Block Nos.1, 2, 3, 4, 5, 6 - Type–A:… RERA registered?
Yes — registered with TNRERA as TN/14/Building/0037/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Construction of 6 Blocks of Block Nos.1, 2, 3, 4, 5, 6 - Type–A:… be completed?
The RERA-committed completion date is 1 Dec 2023. No deadline extensions are on record.
Who is the builder of Construction of 6 Blocks of Block Nos.1, 2, 3, 4, 5, 6 - Type–A:…?
THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board, Cuddalore Division, with 11 projects on the TNRERA register and no completion-date extensions on record.
← All Myladuthurai District projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.