Chikadhasampalayam Scheme
Chikadhasampalayam Scheme is registered with TNRERA as TN/11/Building/0404/2020 (Building registration, 2020). The promoter is The Executive Engineer, TNSCB, Tamil Nadu Slum Clearance Board, Coimbatore Division, who has 33 projects on the TNRERA register. The RERA-committed completion date is 31 Aug 2023 — that date has now passed. Committed dates are legally binding under RERA.
About this registration
Project Name: “Chikadhasampalayam Scheme” - Construction of Block - A of Ground Floor + 3 Floors with 32 tenements, Block - B, C, D, E, F of Ground Floor + 3 Floors with 64 tenements in each Block and by totalling 320 tenements and by totalling altogether 352 tenements Comprised in S.No.522/1 of Chikadhasampalayam Village & Panchayat, Mettupalayam Taluk, Coimbatore District.
Approval: Technical Sanction accorded by the Joint Director, T&CP, Coimbatore District vide Letter No. 1620/2020/CD, dated 08.09.2020 and Building Permission issued by the President, 1st Grade Panchayat, Chikadhasampalayam vide Le
Status on register: Progress of Work as on March 2023
Builder track record: The Executive Engineer, TNSCB, Tamil Nadu Slum Clearance Boa
The Executive Engineer, TNSCB, Tamil Nadu Slum Clearance Board, Coimbatore Division has 33 projects on the TNRERA register since 2020, with no completion-date extensions on record. See the full record →
Frequently asked
Is Chikadhasampalayam Scheme RERA registered?
Yes — registered with TNRERA as TN/11/Building/0404/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Chikadhasampalayam Scheme be completed?
The RERA-committed completion date is 31 Aug 2023. No deadline extensions are on record.
Who is the builder of Chikadhasampalayam Scheme?
The Executive Engineer, TNSCB, Tamil Nadu Slum Clearance Board, Coimbatore Division, with 33 projects on the TNRERA register and no completion-date extensions on record.
← All Coimbatore District projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.