Construction of Stilt Floor + 3 Floors
Construction of Stilt Floor + 3 Floors is registered with TNRERA as TN/10/Building/350/2023 (Building registration, 2023). The promoter is M/s. Anugragha Promoters, who has 2 projects on the TNRERA register. The RERA-committed completion date is 11 Feb 2028 (about 19 months away). Committed dates are legally binding under RERA.
About this registration
Construction of Stilt Floor + 3 Floors Residential Building with 12 dwelling units comprised in R.S.F.No.173/2B1, Old S.F.No.146, Ward No.31, Zone-III of Villarasampatti 'B' Village, Erode Taluk, Erode District.
Approval: The Deputy Director (i/c), T&CP, Erode District issued Planning Permission in Letter RC.No. 3817/2022/ED3, dated 15.11.2022. The Commissioner, Erode LPA issued Building Permission No. 056/BL/2023/00125, dated 13.02.2023
Builder track record: M/s. Anugragha Promoters
M/s. Anugragha Promoters has 2 projects on the TNRERA register since 2023, with no completion-date extensions on record. See the full record →
Frequently asked
Is Construction of Stilt Floor + 3 Floors RERA registered?
Yes — registered with TNRERA as TN/10/Building/350/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Construction of Stilt Floor + 3 Floors be completed?
The RERA-committed completion date is 11 Feb 2028. No deadline extensions are on record.
Who is the builder of Construction of Stilt Floor + 3 Floors?
M/s. Anugragha Promoters, with 2 projects on the TNRERA register and no completion-date extensions on record.
← All Erode District projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.