Construction of Periyar Nagar - Pocket I - Block-A of GF + 3F
Construction of Periyar Nagar - Pocket I - Block-A of GF + 3F is registered with TNRERA as TN/10/Building/0464/2020 (Building registration, 2020). The promoter is THE EXECUTIVE ENGINEER & ADO, who has 40 projects on the TNRERA register. The RERA-committed completion date is 10 Jan 2022 — that date has now passed. Committed dates are legally binding under RERA.
About this registration
Construction of Periyar Nagar - Pocket I - Block-A of GF + 3F with 48 tenements & Block-B of GF + 3F with 44 tenements, Pocket II - Block-B of GF + 3F with 12 tenements, Pocket III - Block-A of GF + 3F with 16 tenements, Pocket III - Block-B of GF + 3F with 104 tenements & Block-C of GF + 3F with 112 tenements and by totalling 336 tenements comprised in T.S.Nos.606/1 part, 910/A part, Ward-E, Block No.23 of Periyar Nagar, Erode Corporation. Perumpallam Odai - Type-A of GF + 6F with 22 tenements in each Floor and by totalling 150 tenements, Type-B of GF + 6F with 20 tenements in each Floor and by totalling 137 tenements, Type-C of GF + 6F with 26 tenements in each Floor and by totalling 177 t
Approval: Periyar Nagar - Planning Permission issued by the Commissioner, T&CP, Chennai vide Letter No. 11987/2017/BA-2, dated 23.09.2017. Planning Permission issued by the Member Secretary (I/C), Erode LPA vide Letter No. 824/201
Status on register: Progress of Work as on March 2022
Builder track record: THE EXECUTIVE ENGINEER & ADO
THE EXECUTIVE ENGINEER & ADO has 40 projects on the TNRERA register since 2018, with no completion-date extensions on record. See the full record →
Frequently asked
Is Construction of Periyar Nagar - Pocket I - Block-A of GF + 3F RERA registered?
Yes — registered with TNRERA as TN/10/Building/0464/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Construction of Periyar Nagar - Pocket I - Block-A of GF + 3F be completed?
The RERA-committed completion date is 10 Jan 2022. No deadline extensions are on record.
Who is the builder of Construction of Periyar Nagar - Pocket I - Block-A of GF + 3F?
THE EXECUTIVE ENGINEER & ADO, with 40 projects on the TNRERA register and no completion-date extensions on record.
← All Erode District projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.