VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Salem District/Sri Hari Tower

Sri Hari Tower

TN/07/Building/0352/2021PAST COMMITTED DATE

Sri Hari Tower is registered with TNRERA as TN/07/Building/0352/2021 (Building registration, 2021). The promoter is Thiru. K.M.Ponam Poosari. The RERA-committed completion date is 8 Nov 2025 — that date has now passed. Committed dates are legally binding under RERA.

11 Oct 2021
8 Nov 2025
16
0

About this registration

Project Name: “Sri Hari Tower” - Construction of Stilt Floor + 4 Floors residential building with 16 dwelling units comprised in Old S.No.52/5A pt, 52/5C pt, New Ward–F, Block No.09, T.S.No.158/4, 159/2, Plot No.19, 20, 21, 22 of Shanthi Nagar, Mitta Ayyamperumampatti Village, Salem District.

Approval: The Assistant Director, T&CP, Salem Region issued Planning Permission in Letter RC No. 2677/2020SR, dated 09.11.2020. The Commissioner, Salem Corporation issued Building Permit No. E-10/296/2020 in Letter No. E-10/362/20

Builder track record: Thiru. K.M.Ponam Poosari

Thiru. K.M.Ponam Poosari has 1 project on the TNRERA register since 2021, with no completion-date extensions on record.

Frequently asked

Is Sri Hari Tower RERA registered?

Yes — registered with TNRERA as TN/07/Building/0352/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Sri Hari Tower be completed?

The RERA-committed completion date is 8 Nov 2025. No deadline extensions are on record.

Who is the builder of Sri Hari Tower?

Thiru. K.M.Ponam Poosari.

← All Salem District projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.