Construction of Residential Tenements of Block - 1, 7, 9 - Ground F…
Construction of Residential Tenements of Block - 1, 7, 9 - Ground F… is registered with TNRERA as TN/07/Building/0140/2020 (Building registration, 2020). The promoter is THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board, who has 10 projects on the TNRERA register. The RERA-committed completion date is —. Committed dates are legally binding under RERA.
About this registration
Construction of Residential Tenements of Block - 1, 7, 9 - Ground Floor + 3 Floors with total 192 dwelling units, Block - 2, 3, 4, 5, 6 - Ground Floor + 3 Floors with total 240 dwelling units, Block - 8, 10 - Ground Floor + 3 Floors with total 64 dwelling units (Totally 496 dwelling units) comprised in S.No.41/1part at Selathampatty Village, Salem District.
Approval: The Member-Secretary, Salem LPA, issued Planning Permission No.59 A to 59 D/2019 in Letter RC No.4412/2018LPA, dated 5.11.2019. The BDO, Salem sanctioned the Building Permission in Letter No.3188/2019/T2, dated 29.01.202
Status on register: Progress of Work as on December 2023
Builder track record: THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board
THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board has 10 projects on the TNRERA register since 2020, with no completion-date extensions on record. See the full record →
Frequently asked
Is Construction of Residential Tenements of Block - 1, 7, 9 - Ground F… RERA registered?
Yes — registered with TNRERA as TN/07/Building/0140/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Construction of Residential Tenements of Block - 1, 7, 9 - Ground F… be completed?
The RERA-committed completion date is —. No deadline extensions are on record.
Who is the builder of Construction of Residential Tenements of Block - 1, 7, 9 - Ground F…?
THE EXECUTIVE ENGINEER, Tamilnadu Slum Clearance Board, with 10 projects on the TNRERA register and no completion-date extensions on record.
← All Salem District projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.