Construction of 2 Blocks of Block 1 – Stilt floor + 4 floors
Construction of 2 Blocks of Block 1 – Stilt floor + 4 floors is registered with TNRERA as TN/02/Building/0254/2018 (Building registration, 2018). The promoter is M/s. Adithi Deep Housing Pvt. Ltd., (previously M/s. Adithi Housing Development Pvt. Ltd.,). The RERA-committed completion date is 31 Jul 2019 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing
Stage, as filed: Block/Tower, Floor wise (Completion Certificate obtained)
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
Apartment sizes (carpet area)
RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.
| Configuration | Carpet area (sq.ft) | Units |
|---|---|---|
| 2BHK | 415–591 | 42 |
Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗
About this registration
Construction of 2 Blocks of Block 1 – Stilt floor + 4 floors with 94 dwelling units and Block – 2 – Stilt floor + 4 Floors with 92 dwelling units (Total 186 dwelling units at S.Nos.78/2B and 79 of Adayalampattu Village, Ambattur Taluk, Tiruvallur District.
Approval: Approved by CMDA Planning Permission No. B/Spl.Bldg./249 A to G/2013 in letter No.B3/18005/2012 dated 19/07/2013, the President, Adayalampattu Panchayat Building Permission No.10/2013 dated 05.09.2013 and Renewal of Plan
Status on register: Progress of Work as on December 2022
Builder track record: M/s. Adithi Deep Housing Pvt. Ltd., (previously M/s. Adithi
M/s. Adithi Deep Housing Pvt. Ltd., (previously M/s. Adithi Housing Development Pvt. Ltd.,) has 1 project on the TNRERA register since 2018, with no completion-date extensions on record.
Frequently asked
Is Construction of 2 Blocks of Block 1 – Stilt floor + 4 floors RERA registered?
Yes — registered with TNRERA as TN/02/Building/0254/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Construction of 2 Blocks of Block 1 – Stilt floor + 4 floors be completed?
The RERA-committed completion date is 31 Jul 2019. No deadline extensions are on record.
Who is the builder of Construction of 2 Blocks of Block 1 – Stilt floor + 4 floors?
M/s. Adithi Deep Housing Pvt. Ltd., (previously M/s. Adithi Housing Development Pvt. Ltd.,).
← All Ambattur–Avadi Belt projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.