Home/Localities/Ambattur–Avadi Belt/Construction of Basement Floor + Stilt Floor + 4 Floors

Construction of Basement Floor + Stilt Floor + 4 Floors

TN/02/Building/0202/2023REGISTERED

Construction of Basement Floor + Stilt Floor + 4 Floors is registered with TNRERA as TN/02/Building/0202/2023 (Building registration, 2023). The promoter is M/s. Nature Residences Development Pvt. Ltd., The Workvilla Kamala Arcade. The RERA-committed completion date is 31 Dec 2027 (about 18 months away). Committed dates are legally binding under RERA.

12 May 2023
31 Dec 2027
147
0

Latest quarterly progress filing

98%
97%

Stage, as filed: A Block- All are completed B Block C Block D Block E Block

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Construction of Basement Floor + Stilt Floor + 4 Floors Residential Building with 147 dwelling units (including Club House & Gym in 1st Floor) comprised in Old S.Nos.132 part, 139/1, T.S.Nos.15/2 – 2, 15/4 – 2/2, 15/4 – 1, Block No.22, Ward–G of Athipattu Village, Ambattur Taluk, Thiruvallur District.

Approval: Planning Permission issued by The Member Secretary / CMDA / Chennai vide Letter No. B3/16445/2015, dated 20.12.2017. Building Permission issued by The Executive Engineer (T.P.) / Greater Chennai Corporation / Chennai vid

Status on register: Progress of Work as on September 2025

Builder track record: M/s. Nature Residences Development Pvt. Ltd., The Workvilla

M/s. Nature Residences Development Pvt. Ltd., The Workvilla Kamala Arcade has 1 project on the TNRERA register since 2023, with no completion-date extensions on record.

Frequently asked

Is Construction of Basement Floor + Stilt Floor + 4 Floors RERA registered?

Yes — registered with TNRERA as TN/02/Building/0202/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Basement Floor + Stilt Floor + 4 Floors be completed?

The RERA-committed completion date is 31 Dec 2027. No deadline extensions are on record.

Who is the builder of Construction of Basement Floor + Stilt Floor + 4 Floors?

M/s. Nature Residences Development Pvt. Ltd., The Workvilla Kamala Arcade.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.