Home/Localities/Ambattur–Avadi Belt/Construction of MSB Group Development having 4 Blocks with combined…

Construction of MSB Group Development having 4 Blocks with combined…

TN/02/Building/0190/2018PAST COMMITTED DATE

Construction of MSB Group Development having 4 Blocks with combined… is registered with TNRERA as TN/02/Building/0190/2018 (Building registration, 2018). The promoter is M/s. Dawning Developers LLP. The RERA-committed completion date is 30 Nov 2020 — that date has now passed. Committed dates are legally binding under RERA.

6 Jun 2018
30 Nov 2020
513
0

Latest quarterly progress filing — June 2023

100%
100%

Stage, as filed: Block/Tower, Floor wise

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
5BHK2,2229
4BHK1,48840
2BHK433–929280
3BHK1,059–1,101148

78% of units have a balcony on the filed area statement, typically around 437 sq.ft.

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of MSB Group Development having 4 Blocks with combined basement floor + combined Stilt floor + combined First floor parking and Gym + combined podium and swimming pool at 2nd floor level for Block-I, Block-II & Block-III. Block-I consists of 2nd floor to 21 floors with 89 dwelling units, Block-II consists of 2nd floor to 21 floors with 160 dwelling units, Block-III consists of 2nd floor to 21 floors with 160 dwelling units, Block-IV consists of stilt floor + 13 floors with 104 LIG dwelling units totally 513 dwelling units at Old Survey Numbers: 122/2A, 122/2B, 123/1B, 123/2B, 123/1A2, 123/2A2, 123/1C1(pt), 123/2C1, 123/1C2, 123/2C2, 123/2C3(pt), 123/2D(pt), 123/1(pt), 123/1A1, 1

Approval: Approved by CMDA vide C/PP/MSB/19(A to O)/2018 in Letter No. C3(N)/7611/2017 dated 21.05.2018 and the Building permission issued by the Greater Chennai Corporation vide Letter No. CEBA/WDCNo.7/00147/2018 dated 25.05.2018

Status on register: Progress of Work as on June 2023

Builder track record: M/s. Dawning Developers LLP

M/s. Dawning Developers LLP has 1 project on the TNRERA register since 2018, with no completion-date extensions on record.

Frequently asked

Is Construction of MSB Group Development having 4 Blocks with combined… RERA registered?

Yes — registered with TNRERA as TN/02/Building/0190/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of MSB Group Development having 4 Blocks with combined… be completed?

The RERA-committed completion date is 30 Nov 2020. No deadline extensions are on record.

Who is the builder of Construction of MSB Group Development having 4 Blocks with combined…?

M/s. Dawning Developers LLP.

← All Ambattur–Avadi Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.