Construction of Block:A - Stilt Floor (Parking) + 1st Floor to 13 F…
Construction of Block:A - Stilt Floor (Parking) + 1st Floor to 13 F… is registered with TNRERA as TN/02/Building/0020/2022 (Building registration, 2022). The promoter is 1) Thiru. S.Kadirvelu. The RERA-committed completion date is 16 Jun 2026 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing — MARCH 2023
Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 30% physical completion. Ask the builder for the current status and updated timeline before paying anything.
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
Apartment sizes (carpet area)
RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.
| Configuration | Carpet area (sq.ft) | Units |
|---|---|---|
| 2BHK | 429–682 | 80 |
| 3BHK | 604–869 | 38 |
| 8BHK | 253–559 | 2 |
75% of units have a balcony on the filed area statement, typically around 32 sq.ft.
Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗
About this registration
Construction of Block:A - Stilt Floor (Parking) + 1st Floor to 13 Floor with 195 dwelling units, Block:B - Stilt Floor (Parking) + 1st Floor to 13 Floor with 104 dwelling units, Block:C – Ground Floor + 1st Floor to 4 Floor (for shop) and by totalling altogether 299 dwelling units at Old Door No.4, New Door No.13/6, Jawaharlal Nehru Salai (Inner Ring Road), Thathankuppam, Villivakkam, Chennai – 600049 comprised in Old S.No.99/1, 99/2, 157/1A, 159 part, 161/2, T.S.No.9, 10/2, 11/5 & 11/6, Block No.31, Ward No–‘E’ of Korattur Village, Ambattur Taluk, Tiruvallur District.
Approval: Planning Permission issued by The Member Secretary / CMDA / Chennai vide Letter No. C3(N)/0236/2019, dated 26/7/2021. Building Permission issued by The Executive Engineer (T.P.) / Greater Chennai Corporation / Chennai vi
Status on register: Progress of Work as on June 2024
Planning permission for this project was issued by CMDA (read from the approval document on the TNRERA register).
Builder track record: 1) Thiru. S.Kadirvelu
1) Thiru. S.Kadirvelu has 1 project on the TNRERA register since 2022, with no completion-date extensions on record.
Frequently asked
Is Construction of Block:A - Stilt Floor (Parking) + 1st Floor to 13 F… RERA registered?
Yes — registered with TNRERA as TN/02/Building/0020/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Construction of Block:A - Stilt Floor (Parking) + 1st Floor to 13 F… be completed?
The RERA-committed completion date is 16 Jun 2026. No deadline extensions are on record.
Who is the builder of Construction of Block:A - Stilt Floor (Parking) + 1st Floor to 13 F…?
1) Thiru. S.Kadirvelu.
← All North Chennai projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.