Orion is registered with TNRERA as TN/01/Building/135/2019 (Building registration, 2019). The promoter is M/s. STELLAR DEVELOPER. The RERA-committed completion date is —. Committed dates are legally binding under RERA.

14 Sep 2019
51
0

Latest quarterly progress filing

40%

Stage, as filed: Block/Tower, Floor wise Completed,Sill level Block work Completed

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
3BHK894–9048
2BHK609–89325

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Project Name: “Orion” - Construction of Block A - Stilt Floor + 4th Floor + 5th Floor part, Block B - Stilt Floor + 4th Floor + 5th Floor part totalling to 51 dwelling units comprised in Old S.No.470 pt (as per Doc) and New S.No.470/2 (as per Patta) of Manapakkam Village at Plot No.2, Existing Tiruvalluvar Nagar Road, Mannapakkam-Alandur Taluk, Kancheepuram District.

Approval: Approved by the Chief Planner(Area Plans Unit) CMDA Egmore, Chennai-8 vide Letter No.PP/SB/S/0293/2019 dated 27.06.19 and Building Permission approved by the Executive Engineer(TP) of Greater Chennai Corporation vide CEB

Status on register: Progress of Work as on December 2019

Builder track record: M/s. STELLAR DEVELOPER

M/s. STELLAR DEVELOPER has 1 project on the TNRERA register since 2019, with no completion-date extensions on record.

Frequently asked

Is Orion RERA registered?

Yes — registered with TNRERA as TN/01/Building/135/2019 in 2019. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Orion be completed?

The RERA-committed completion date is —. No deadline extensions are on record.

Who is the builder of Orion?

M/s. STELLAR DEVELOPER.

← All Porur Belt projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.