Pelican Shrishti Phase II-A

TN/01/Building/0455/2020PAST COMMITTED DATE

Pelican Shrishti Phase II-A is registered with TNRERA as TN/01/Building/0455/2020 (Building registration, 2020). The promoter is M/s. MAK Pelican Realty Ventures LLP. The RERA-committed completion date is 30 Aug 2022 — that date has now passed. Committed dates are legally binding under RERA.

8 Dec 2020
30 Aug 2022
12
0

Latest quarterly progress filing — June 2023

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 40% physical completion. Ask the builder for the current status and updated timeline before paying anything.

40%

Stage, as filed: Block/Tower, Floor wise COLUMN CONCRETE IN PROGRESS

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Pelican Shrishti Phase II-A” - Construction of Stilt Floor + 3 Floors with 12 dwelling units at Plot Nos.22, 23 comprised in S.Nos.275/11A2, 275/11B2 of Pudhupattinam Village and Panchayat, Thirukazhukundram Taluk, Chengalpattu District.

Approval: Planning Permission issued by the Member-Secretary, Mamallapuram LPA vide Letter No.1494/2019/MLPA, dated 14.02.2020 and the Building Permission issued by the Special Officer/Pudhupattinam Panchayat, BDO (VP)/Thirukazhuk

Status on register: Progress of Work as on December 2024

Builder track record: M/s. MAK Pelican Realty Ventures LLP

M/s. MAK Pelican Realty Ventures LLP has 1 project on the TNRERA register since 2020, with no completion-date extensions on record.

Frequently asked

Is Pelican Shrishti Phase II-A RERA registered?

Yes — registered with TNRERA as TN/01/Building/0455/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Pelican Shrishti Phase II-A be completed?

The RERA-committed completion date is 30 Aug 2022. No deadline extensions are on record.

Who is the builder of Pelican Shrishti Phase II-A?

M/s. MAK Pelican Realty Ventures LLP.

← All Chengalpattu District projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.