Home/Localities/Kancheepuram District/Raja Castle

Raja Castle

TN/01/Building/0406/2020PAST COMMITTED DATE

Raja Castle is registered with TNRERA as TN/01/Building/0406/2020 (Building registration, 2020). The promoter is Thiru. Sethu Raja, Proprietor, M/s. Raja Builders and Developers. The RERA-committed completion date is 31 Jan 2023 — that date has now passed. Committed dates are legally binding under RERA.

5 Nov 2020
31 Jan 2023
11
0

Latest quarterly progress filing — March 2021

Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 70% physical completion. Ask the builder for the current status and updated timeline before paying anything.

70%
70%

Stage, as filed: Brick work and internal plastering completed. Second floor brick work under progress.

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Raja Castle” - Construction of Stilt Floor + 2 Floors + 3rd Floor part residential building with 11 dwelling units at Plot No.7, Door No.3, Appu Street, Chamundeeswari Nagar, Pammal, Chennai, comprised in S.No.180/42 of Pammal Village, Kancheepuram District.

Approval: Planning Permission issued by CMDA in Letter No. PP/NHRB/S(B1)/1224/2019, dated 10.03.2020. Building Permission issued by The Commissioner, Pammal Municipality in Letter No. 46/2020/F1, dated 19.05.2020

Status on register: Progress of Work as on March 2021

Builder track record: Thiru. Sethu Raja, Proprietor, M/s. Raja Builders and Develo

Thiru. Sethu Raja, Proprietor, M/s. Raja Builders and Developers has 1 project on the TNRERA register since 2020, with no completion-date extensions on record.

Frequently asked

Is Raja Castle RERA registered?

Yes — registered with TNRERA as TN/01/Building/0406/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Raja Castle be completed?

The RERA-committed completion date is 31 Jan 2023. No deadline extensions are on record.

Who is the builder of Raja Castle?

Thiru. Sethu Raja, Proprietor, M/s. Raja Builders and Developers.

← All Kancheepuram District projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.