Isha Code Field - Phase V
Isha Code Field - Phase V is registered with TNRERA as TN/01/Building/0285/2021 (Building registration, 2021). The promoter is M/s. Isha Homes (india) Private Limited, who has 16 projects on the TNRERA register. The RERA-committed completion date is —. Committed dates are legally binding under RERA.
About this registration
Project Name: “Isha Code Field - Phase V” - Construction of Plot No.73 - Ground Floor + First Floor with one dwelling unit, Plot No.75 - Ground Floor + First Floor with one dwelling unit, Plot No.87 - Ground Floor + First Floor with one dwelling unit, Plot No.88 - Ground Floor + First Floor with one dwelling unit, Plot No.89 - Ground Floor + First Floor with one dwelling unit, Plot No.90 - Ground Floor + First Floor with one dwelling unit, Plot No.99 - Ground Floor + First Floor with one dwelling unit, Plot No.103 - Ground Floor + First Floor with one dwelling unit, Plot No.130 - Ground Floor + First Floor with one dwelling unit comprised in S.Nos.64/10B, 12, 13, 65/1, 2, 6, 8A & 9B of Pudup
Approval: Planning Permission issued by the Special Officer / Pudupakkam Panchayat / BDO (V.P) / Thiruporur Panchayat Union for Plot No.73 vide Letter No.13/2021/VI dated 19.06.2021, Plot No.75 vide Letter No.15/2021/VI dated 19.0
Status on register: Progress of Work as on December 2023
Builder track record: M/s. Isha Homes (india) Private Limited
M/s. Isha Homes (india) Private Limited has 16 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →
Frequently asked
Is Isha Code Field - Phase V RERA registered?
Yes — registered with TNRERA as TN/01/Building/0285/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Isha Code Field - Phase V be completed?
The RERA-committed completion date is —. No deadline extensions are on record.
Who is the builder of Isha Code Field - Phase V?
M/s. Isha Homes (india) Private Limited, with 16 projects on the TNRERA register and no completion-date extensions on record.
← All OMR Corridor projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.