Home/Localities/OMR Corridor/Construction of Ground Floor+ 2 Floors (44 Villas) and Stilt Floor+…

Construction of Ground Floor+ 2 Floors (44 Villas) and Stilt Floor+…

TN/01/Building/0171/2017PAST COMMITTED DATE

Construction of Ground Floor+ 2 Floors (44 Villas) and Stilt Floor+… is registered with TNRERA as TN/01/Building/0171/2017 (Building registration, 2017). The promoter is M/s. Malles Constructions Pvt. Ltd., who has 7 projects on the TNRERA register. The RERA-committed completion date is 31 Dec 2020 — that date has now passed. Committed dates are legally binding under RERA.

8 Nov 2017
31 Dec 2020
100
0

Latest progress filing

The project's most recent quarterly filing on the TNRERA register references completion certificate — a completion-stage document. Ask the builder for the certificate and current possession status.

From the quarterly progress filing

The builder's filing references a completion certificate — a sign of completion. Confirm the certificate directly with the builder or on the TNRERA portal.

Read from a scanned quarterly filing via OCR. Verify against the source before relying on it.

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

Carpet areas range from 1,396 to 2,278 sq.ft (median 1,837 sq.ft) across 2 units.

Machine-read from the filed carpet-area statement (low OCR confidence — verify against source). Normalised to sq.ft. View the original document filed with TNRERA ↗

About this registration

Construction of Ground Floor+ 2 Floors (44 Villas) and Stilt Floor+ 2 Floors of 14 Blocks with 56 Dwelling Units (Total 100 Units) at S.No.122/4A, 127, 130/2, 3, 133/1, 135/2B, 3, 136 & 138/2, 3 of Perumbakkam Village, Sholinganallur Taluk, Kancheepuram District.

Approval: Approved by the Commissioner, St.Thomas Mount Panchayath Union D.Dis.1148/2017 - P.P.No.912/2017 dated 05.07.2017 etc., and Approved by the Special Office, Perumbakkam, Panchyath BL No.72/2017 - 2018 dated 08.08.2017 etc

Status on register: Progress of Work as on June 2022

Builder track record: M/s. Malles Constructions Pvt. Ltd.

M/s. Malles Constructions Pvt. Ltd. has 7 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of Ground Floor+ 2 Floors (44 Villas) and Stilt Floor+… RERA registered?

Yes — registered with TNRERA as TN/01/Building/0171/2017 in 2017. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Ground Floor+ 2 Floors (44 Villas) and Stilt Floor+… be completed?

The RERA-committed completion date is 31 Dec 2020. No deadline extensions are on record.

Who is the builder of Construction of Ground Floor+ 2 Floors (44 Villas) and Stilt Floor+…?

M/s. Malles Constructions Pvt. Ltd., with 7 projects on the TNRERA register and no completion-date extensions on record.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.