Casagrand Aspires
Casagrand Aspires is registered with TNRERA as TN/01/Building/0158/2023 (Building registration, 2023). The promoter is M/s. Danub Homes Private Limited, who has 3 projects on the TNRERA register. The RERA-committed completion date is 3 Oct 2025 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing — December 2025
Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 42% physical completion. Ask the builder for the current status and updated timeline before paying anything.
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
About this registration
Project Name: “Casagrand Aspires” - Construction of Registration of Basement Stilt Floor + Podium & Swimming Pool on 1st Floor Level with Club House partly + 18 Upper Floors, Totally 316 Dwelling units comprised in S.No.103/7 of Karanai Village, Vandalur Taluk, Chengalpet District.
Approval: The Director, T&CP, Chennai issued Technical Concurrence in Letter No. SWP/BPA/0004938/2022, dated 07.03.2023. The Assistant Director, T&CP, Chengalpet District issued the Planning Permission in Letter No. SWP/BPA/000493
Status on register: Progress of Work as on December 2025
Builder track record: M/s. Danub Homes Private Limited
M/s. Danub Homes Private Limited has 3 projects on the TNRERA register since 2023, with no completion-date extensions on record. See the full record →
Frequently asked
Is Casagrand Aspires RERA registered?
Yes — registered with TNRERA as TN/01/Building/0158/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Casagrand Aspires be completed?
The RERA-committed completion date is 3 Oct 2025. No deadline extensions are on record.
Who is the builder of Casagrand Aspires?
M/s. Danub Homes Private Limited, with 3 projects on the TNRERA register and no completion-date extensions on record.
← All GST Road South projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.