TN/01/Building/0146/2023PAST COMMITTED DATE

Rohaan Phoenix is registered with TNRERA as TN/01/Building/0146/2023 (Building registration, 2023). The promoter is M/s. Rohaan Constructions (P) Ltd., First Floor, who has 3 projects on the TNRERA register. The RERA-committed completion date is 31 Dec 2025 — that date has now passed. Committed dates are legally binding under RERA.

3 Apr 2023
31 Dec 2025
12
0

Latest quarterly progress filing — December 2024

100%

Stage, as filed: Floor wise Floors

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Rohaan Phoenix” - Construction of Stilt Floor + 3 Floors Residential Building with 12 dwelling units at Neela Nagar 1st Main Road, Medavakkam, Chennai comprised in S.No.427/281 of Medavakkam Village, Tambaram Taluk, Chengalpattu District.

Approval: Planning Permission issued by The Member Secretary / CMDA / Chennai vide Letter No. CMDA/PP/NHRB/S/0501/2022, dated 08.02.2023. Building Permission issued by The President / Executive Officer / Medavakkam 1st Grade Villa

Status on register: Progress of Work as on December 2024

Builder track record: M/s. Rohaan Constructions (P) Ltd., First Floor

M/s. Rohaan Constructions (P) Ltd., First Floor has 3 projects on the TNRERA register since 2021, with no completion-date extensions on record. See the full record →

Frequently asked

Is Rohaan Phoenix RERA registered?

Yes — registered with TNRERA as TN/01/Building/0146/2023 in 2023. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Rohaan Phoenix be completed?

The RERA-committed completion date is 31 Dec 2025. No deadline extensions are on record.

Who is the builder of Rohaan Phoenix?

M/s. Rohaan Constructions (P) Ltd., First Floor, with 3 projects on the TNRERA register and no completion-date extensions on record.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.