Casagrand First City
Casagrand First City is registered with TNRERA as TN/01/Building/0114/2021 (Building registration, 2021). The promoter is M/s. Danub Homes Pvt. Ltd., – for self and POA of M/s. Casa Grande Milestone Pvt. Ltd.. The RERA-committed completion date is 4 Dec 2024 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing — December, 2023
Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 63% physical completion. Ask the builder for the current status and updated timeline before paying anything.
Stage, as filed: Block/Tower, Floor wise
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
About this registration
Project Name: "Casagrand First City" - Construction of 2 Blocks consisting of Block-A: Extended Basement Floor + Stilt Floor + 1st Floor (Podium Level with Swimming Pool + 2nd Floor to 16 Floor with 1693 Dwelling Units and Block-B: Ground Floor + 3 Floors with Swimming Pool at Ground level comprised in S.Nos.470, 471, 472/1, 472/2, 476/1B of Perumbakkam Village, Tambaram Taluk, Kancheepuram District.
Approval: Planning Permission issued by CMDA in Letter No. C3(S)/494/2019, dated 27.08.2020. The Commissioner, St. Thomas Mount Panchayat Union forwarded to Special Officer, Perumbakkam, Letter RC No.3299/2020/A4, dated 01.09.2020
Status on register: Progress of Work as on December 2025
Builder track record: M/s. Danub Homes Pvt. Ltd., – for self and POA of M/s. Casa
M/s. Danub Homes Pvt. Ltd., – for self and POA of M/s. Casa Grande Milestone Pvt. Ltd. has 1 project on the TNRERA register since 2021, with no completion-date extensions on record.
Frequently asked
Is Casagrand First City RERA registered?
Yes — registered with TNRERA as TN/01/Building/0114/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Casagrand First City be completed?
The RERA-committed completion date is 4 Dec 2024. No deadline extensions are on record.
Who is the builder of Casagrand First City?
M/s. Danub Homes Pvt. Ltd., – for self and POA of M/s. Casa Grande Milestone Pvt. Ltd..
← All OMR Corridor projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.