VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/Sriperumbudur–Oragadam/Construction of Combined Basement Floor – Block – 11, Ground fl…

Construction of Combined Basement Floor – Block – 11, Ground fl…

TN/01/Building/0101/2018PAST COMMITTED DATE

Construction of Combined Basement Floor – Block – 11, Ground fl… is registered with TNRERA as TN/01/Building/0101/2018 (Building registration, 2018). The promoter is M/s. AMARPRAKASH DEVELOPERS (P) LTD., who has 13 projects on the TNRERA register. The RERA-committed completion date is 31 Dec 2021 — that date has now passed. Committed dates are legally binding under RERA.

26 Mar 2018
31 Dec 2021
65
0

A quarterly progress filing exists for this project on the TNRERA register as a scanned document; we haven't machine-read it yet.

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
2BHK58026
3BHK957–96721

3% of units have a balcony on the filed area statement, typically around 296 sq.ft.

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Construction of Combined Basement Floor – Block – 11, Ground floor + 6 floors residential building with 65 dwelling units at S.Nos.124/2, 228/2, 229/3, 230, 231/1, 231/2, 232/1B, 232/2, 233/1B, 233/2B, 241, 242/1A, 243/1, 243/2A, 243/2B, 244, 248/2A2 & 248/2A3A Thirumudivakkam Main Road, Thirumudivakkam Village, Sriperumbudur Taluk, Kancheepuram District.

Approval: Approved by CMDA PP No: C/PP/MSB/54 (S1 to S49) / 2015 in letter No.C3(S)/14609/2014 dated 30.12.2015 and the President / Executive Officer, Thirumudivakkam Panchayat Building permission letter No.1/2016-17 dated 1.6.201

Status on register: Progress of Work as on September 2019

Planning permission for this project was issued by CMDA (read from the approval document on the TNRERA register).

Builder track record: M/s. AMARPRAKASH DEVELOPERS (P) LTD.

M/s. AMARPRAKASH DEVELOPERS (P) LTD. has 13 projects on the TNRERA register since 2018, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of Combined Basement Floor – Block – 11, Ground fl… RERA registered?

Yes — registered with TNRERA as TN/01/Building/0101/2018 in 2018. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Combined Basement Floor – Block – 11, Ground fl… be completed?

The RERA-committed completion date is 31 Dec 2021. No deadline extensions are on record.

Who is the builder of Construction of Combined Basement Floor – Block – 11, Ground fl…?

M/s. AMARPRAKASH DEVELOPERS (P) LTD., with 13 projects on the TNRERA register and no completion-date extensions on record.

← All Sriperumbudur–Oragadam projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.