Construction of 2 Blocks of Stilt Floor + 5 Floors is registered with TNRERA as TN/01/Building/0078/2021 (Building registration, 2021). The promoter is Thiru. P.Rajesh, Proprietor, M/s. Sudarasan Builders & Developers. The RERA-committed completion date is 31 Dec 2023 — that date has now passed. Committed dates are legally binding under RERA.

2 Mar 2021
31 Dec 2023
50
0

Latest quarterly progress filing — December, 2023

100%

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Construction of 2 Blocks of Stilt Floor + 5 Floors residential building with 25 dwelling units each (Total 50 dwelling units) at New Door No.14, Old Door No.55A, Vijayalakshmi Street, Rajeshwari Nagar, East Tambaram, Chennai - 600073 comprised in T.S.Nos.55 & 83/2, Block No.53, Ward–G and T.S.No.79, Block No.50, Ward-G of Selaiyur Village, Chennai.

Approval: CMDA issued Planning Permission in Letter No. PP/NHRB/S(B1)/1056/2019, dated 18.03.2020. The Commissioner, Tambaram Municipality issued Building Licence No.135/2020 in Letter No.117/2020, dated 12.06.2020

Status on register: Completed

Builder track record: Thiru. P.Rajesh, Proprietor, M/s. Sudarasan Builders & Devel

Thiru. P.Rajesh, Proprietor, M/s. Sudarasan Builders & Developers has 1 project on the TNRERA register since 2021, with no completion-date extensions on record.

Frequently asked

Is Construction of 2 Blocks of Stilt Floor + 5 Floors RERA registered?

Yes — registered with TNRERA as TN/01/Building/0078/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of 2 Blocks of Stilt Floor + 5 Floors be completed?

The RERA-committed completion date is 31 Dec 2023. No deadline extensions are on record.

Who is the builder of Construction of 2 Blocks of Stilt Floor + 5 Floors?

Thiru. P.Rajesh, Proprietor, M/s. Sudarasan Builders & Developers.

← All GST Road South projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.