Anarghya
Anarghya is registered with TNRERA as TN/01/Building/0076/2020 (Building registration, 2020). The promoter is M/s. Jain Housing & Constructions Ltd., who has 10 projects on the TNRERA register. The RERA-committed completion date is 30 Sep 2025 — that date has now passed. Committed dates are legally binding under RERA.
Latest quarterly progress filing
Caution: the RERA-committed completion date has passed, and the last quarterly filing reported 93% physical completion. Ask the builder for the current status and updated timeline before paying anything.
Stage, as filed: Block/Tower, Floor wise Terrace
Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).
About this registration
Project Name: “Anarghya” - Construction of Block A - Stilt + 15 Floors in which the promoter’s share of Flats – 1st Floor Flat Nos. 101 to 110, 2nd Floor Flat Nos. 203, 204, 205, 206 & 207, 3rd Floor Flat Nos. 301 to 310, 4th Floor Flat Nos. 404 & 405, 5th Floor Flat Nos. 503, 504, 505 & 508, 7th Floor Flat Nos. 704 to 708, 8th Floor Flat Nos. 801 to 810, 9th Floor Flat Nos. 903, 908 & 909, 10th Floor Flat Nos. 1001, 1002, 1005, 1006, 1007, 1009 & 1010, 12th Floor Flat Nos. 1201 to 1210, 13th Floor Flat Nos.1303 & 1308, 14th Floor Flat Nos. 1401 to 1410, 15th Floor Flat Nos. 1502, 1503, 1507, 1508 & 1509 comprised in S.No.65/1A, 1B, 669/8A, 8B, 9, 670/5, 6, 7 of Pallikaranai Village, MMRD Ro
Approval: Planning Permission issued by Member-Secretary/CMDA/Egmore/Chennai-8, Vide Letter No.C3(S)/7947/2018, dated 06.12.2019. Building permission issued by Executive Engineer(TP)/Greater Chennai Corporation Vide No.CEBA/WDCN14
Status on register: Progress of Work as on September 2025
Builder track record: M/s. Jain Housing & Constructions Ltd.
M/s. Jain Housing & Constructions Ltd. has 10 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →
Frequently asked
Is Anarghya RERA registered?
Yes — registered with TNRERA as TN/01/Building/0076/2020 in 2020. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.
When will Anarghya be completed?
The RERA-committed completion date is 30 Sep 2025. No deadline extensions are on record.
Who is the builder of Anarghya?
M/s. Jain Housing & Constructions Ltd., with 10 projects on the TNRERA register and no completion-date extensions on record.
← All OMR Corridor projects and market data
Source documents on TNRERA
These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.