VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/OMR Corridor/Sherin Enclave

Sherin Enclave

TN/01/Building/0034/2022PAST COMMITTED DATE

Sherin Enclave is registered with TNRERA as TN/01/Building/0034/2022 (Building registration, 2022). The promoter is 1) Tmt. Anitha Radhakrishnan, Tas Enclave 10th Main Road, AK Block, Anna Nagar, Chennai – 600040 and 2) M/s. S&D Structurals, Sheen Castle. The RERA-committed completion date is 30 Jun 2023 — that date has now passed. Committed dates are legally binding under RERA.

28 Jan 2022
30 Jun 2023
12
0

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
2BHK670–6775

Machine-read from the filed carpet-area statement. Normalised to sq.ft from sq.m. View the original document filed with TNRERA ↗

About this registration

Project Name: “Sherin Enclave” - Construction of Stilt Floor + 3 Floors with 12 dwelling units at Plot–117, 6th Street, Ram Nagar South Extension comprised in New S.No.11/2A2 & 12/1A1B of Pallikaranai Village, Sholinganallur Taluk, Kancheepuram District.

Approval: Planning Permission issued by The Executive Engineer (T.P.) / Greater Chennai Corporation / Chennai vide Letter No. PPA/WDCN14/03851/2021, dated 23/9/2021. Building Permission issued by The Executive Engineer (T.P.) / Gr

Planning permission for this project was issued by Municipal (read from the approval document on the TNRERA register).

Builder track record: 1) Tmt. Anitha Radhakrishnan, Tas Enclave 10th Main Road, AK

1) Tmt. Anitha Radhakrishnan, Tas Enclave 10th Main Road, AK Block, Anna Nagar, Chennai – 600040 and 2) M/s. S&D Structurals, Sheen Castle has 1 project on the TNRERA register since 2022, with no completion-date extensions on record.

Frequently asked

Is Sherin Enclave RERA registered?

Yes — registered with TNRERA as TN/01/Building/0034/2022 in 2022. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Sherin Enclave be completed?

The RERA-committed completion date is 30 Jun 2023. No deadline extensions are on record.

Who is the builder of Sherin Enclave?

1) Tmt. Anitha Radhakrishnan, Tas Enclave 10th Main Road, AK Block, Anna Nagar, Chennai – 600040 and 2) M/s. S&D Structurals, Sheen Castle.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.