Home/Localities/GST Road South/Construction of Multi Storeyed Block B only at S.No. 355/1A, 1B, 35…

Construction of Multi Storeyed Block B only at S.No. 355/1A, 1B, 35…

TN/01/Building/0031/2017PAST COMMITTED DATE

Construction of Multi Storeyed Block B only at S.No. 355/1A, 1B, 35… is registered with TNRERA as TN/01/Building/0031/2017 (Building registration, 2017). The promoter is M/s. Akshaya Pvt. Ltd., GPA holder for M/s. Bharat Promoters, G-Square, who has 2 projects on the TNRERA register. The RERA-committed completion date is 30 Nov 2023 — that date has now passed. Committed dates are legally binding under RERA.

23 Aug 2017
30 Nov 2023
0

Latest quarterly progress filing — DECEMBER 2023

Stage, as filed: slab completed Block/Tower, Floor wise Seventh Floor Roof B2 slab completed

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

Apartment sizes (carpet area)

RERA carpet areas for this project, read from the filed area statement — the real usable floor area, excluding balcony and common space.

ConfigurationCarpet area (sq.ft)Units
2BHK646–834126
3BHK954–97328

100% of units have a balcony on the filed area statement, typically around 39 sq.ft.

Machine-read from the filed carpet-area statement. Normalised to sq.ft. View the original document filed with TNRERA ↗

About this registration

Construction of Multi Storeyed Block B only at S.No. 355/1A, 1B, 356/1A, 2A, 1B, 2B1, 2B2, 412/1, 2 and 357/1A2 of Kovur Village, Tambaram Taluk.

Approval: Approved by CMDA letter no. C3/13278/2012 dated 27.09.2013 and Commissioner, Kundrathur Panchayat Union letter BA No. 4992/2013/A3 dated 11.10.2013 and renewed in CMDA letter no. EC/C-I/14428/2016 dated 31.03.2017 and Co

Status on register: Progress of Work as on June 2025

Planning permission for this project was issued by CMDA (read from the approval document on the TNRERA register).

Builder track record: M/s. Akshaya Pvt. Ltd., GPA holder for M/s. Bharat Promoters

M/s. Akshaya Pvt. Ltd., GPA holder for M/s. Bharat Promoters, G-Square has 2 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Construction of Multi Storeyed Block B only at S.No. 355/1A, 1B, 35… RERA registered?

Yes — registered with TNRERA as TN/01/Building/0031/2017 in 2017. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Construction of Multi Storeyed Block B only at S.No. 355/1A, 1B, 35… be completed?

The RERA-committed completion date is 30 Nov 2023. No deadline extensions are on record.

Who is the builder of Construction of Multi Storeyed Block B only at S.No. 355/1A, 1B, 35…?

M/s. Akshaya Pvt. Ltd., GPA holder for M/s. Bharat Promoters, G-Square, with 2 projects on the TNRERA register and no completion-date extensions on record.

← All GST Road South projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.