VerifyRERAEvery project's full RERA record. Verified in seconds.
Home/Localities/OMR Corridor/Adroit Prosper

Adroit Prosper

TN/01/Building/0010/2021REGISTERED

Adroit Prosper is registered with TNRERA as TN/01/Building/0010/2021 (Building registration, 2021). The promoter is M/s. Adroit Urban Developers Pvt. Ltd., who has 2 projects on the TNRERA register. The RERA-committed completion date is 31 Aug 2026 (about 2 months away). Committed dates are legally binding under RERA.

11 Jan 2021
31 Aug 2026
573
0

Latest quarterly progress filing — DECEMBER 2023

87%

Stage, as filed: for each 50% Completed Block/Tower, Item 2. 10th floor slab concrete wise 100% Completed

Source: the project's Quarterly Progress Report filed with TNRERA (as on the quarter shown; may not reflect current status).

About this registration

Project Name: “Adroit Prosper” - Construction of Block–A: Basement Floor + Stilt Floor + 10 Floors with 15 dwelling units and by totalling 150 dwelling units, Block-B: Basement Floor + Stilt Floor + 9 Floors with 19 dwelling units and by totalling 171 dwelling units, Block-C: Basement Floor + Stilt Floor + 9 Floors with 10 dwelling units and by totalling 90 dwelling units, Block-D: Basement Floor + Stilt Floor + 9 Floors with 18 dwelling units and by totalling 162 dwelling units and by totalling altogether 573 dwelling units and a Club House of Ground Floor + 2 Floors comprised in S.Nos.80/7A & 80/7B of Thalambur Village, Thiruporur Taluk, Kancheepuram District.

Approval: Planning Permission issued by the Member-Secretary, Mamallapuram LPA vide Letter No. 5454/2018/MLPA, dated 19.11.2019 and the Building Permission issued by the Special Officer/Thalambur Panchayat, BDO (VP)/Thiruporur Pan

Status on register: Progress of Work as on December 2025

Builder track record: M/s. Adroit Urban Developers Pvt. Ltd.

M/s. Adroit Urban Developers Pvt. Ltd. has 2 projects on the TNRERA register since 2017, with no completion-date extensions on record. See the full record →

Frequently asked

Is Adroit Prosper RERA registered?

Yes — registered with TNRERA as TN/01/Building/0010/2021 in 2021. Always quote this number when dealing with the builder; unregistered projects cannot legally be marketed or sold in Tamil Nadu.

When will Adroit Prosper be completed?

The RERA-committed completion date is 31 Aug 2026. No deadline extensions are on record.

Who is the builder of Adroit Prosper?

M/s. Adroit Urban Developers Pvt. Ltd., with 2 projects on the TNRERA register and no completion-date extensions on record.

← All OMR Corridor projects and market data

Source documents on TNRERA

These are the government's own filed documents for this project. We link them directly — verify anything on this page against them.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.