Home/Builders/M/s. JAYABHARATH HOMES (P) LTD.

M/s. JAYABHARATH HOMES (P) LTD.

M/s. JAYABHARATH HOMES (P) LTD. has 5 projects on the TNRERA register since 2018 — 162 units/plots in total, concentrated in Madurai District. 0 completion-deadline extensions are recorded across their projects, and 1 projects are past their committed completion dates on the register. All figures from TNRERA public records.

5
2018
162
0

Builder Performance Dashboard

Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.

40%
0%
1
48 mo
100%

Marked completed: share of their 5 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 3 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record. Disclosure completeness: share of key filing fields (stage, building type, site extent, planning permission, units, completion date) present on the detailed register — sampled for 1 of 5 projects.

All TNRERA registrations by M/s. JAYABHARATH HOMES (P) LTD.

ProjectRERA No.LocalityYearCommitted byUnits
TWIN TOWER TN/20/Building/0046/2025 Madurai District 2025 1 Dec 2029 70
ELANZA RA/20/BLG/0268/2025 Madurai District 2025 15 May 2030 40
Registration of Layout TN/20/Layout/0180/2024 Madurai District 2024 52 DONE
Jayabharath Oscar City Extension TN/20/Layout/0270/2021 Madurai District 2021 31 Dec 2023
Regularisation of Layout comprised in S.Nos.10/10, 12/1, 5, 13/3B, 14/11A, 11B, 12B, 18/3A TN/20/Layout/0027/2018 Madurai District 2018 DONE

How to read this record

Does M/s. JAYABHARATH HOMES (P) LTD. deliver on time?

No completion-deadline extensions are recorded across their 5 registered projects — a clean register on this measure.

Where does M/s. JAYABHARATH HOMES (P) LTD. build?

Their registrations concentrate in Madurai District.