M/s. URBANDO HOUSING LLP

M/s. URBANDO HOUSING LLP has 8 projects on the TNRERA register since 2019 — 272 units/plots in total, concentrated in OMR Corridor, Poonamallee Corridor. 0 completion-deadline extensions are recorded across their projects, and 1 projects are past their committed completion dates on the register. All figures from TNRERA public records.

8
2019
272
0

Builder Performance Dashboard

Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.

75%
0%
0
60 mo
100%
3 mo

Marked completed: share of their 8 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 3 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record. Disclosure completeness: share of key filing fields (stage, building type, site extent, planning permission, units, completion date) present on the detailed register — sampled for 1 of 8 projects.Approval → RERA: median months between the planning-approval document date (OCR'd from the filed approval) and RERA registration, across 3 projects where both dates are readable.

All TNRERA registrations by M/s. URBANDO HOUSING LLP

ProjectRERA No.LocalityYearCommitted byUnits
Kosmos Orbiz TN/35/Building/0051/2024 OMR Corridor 2024 31 Dec 2029 43
URBANDO EVORISE TN/35/Building/0607/2024 OMR Corridor 2024 31 Dec 2032 100
Kosmos Terra TN/01/Layout/0249/2023 OMR Corridor 2023 37 DONE
Kosmos Solaris TN/02/Layout/1986/2023 OMR Corridor 2023 45 DONE
Urbando Province TN/01/Layout/0229/2021 OMR Corridor 2021 DONE
Vibha TN/02/Layout/0527/2021 Poonamallee Corridor 2021 35 DONE
Altea TN/29/Building/0183/2020 OMR Corridor 2020 31 Jul 2021 12 DONE
Daksha TN/29/Layout/0215/2019 OMR Corridor 2019 DONE

How to read this record

Does M/s. URBANDO HOUSING LLP deliver on time?

No completion-deadline extensions are recorded across their 8 registered projects — a clean register on this measure.

Where does M/s. URBANDO HOUSING LLP build?

Their registrations concentrate in OMR Corridor, Poonamallee Corridor.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.