The Executive Engineer, TNSCB, Madurai Division, Tamil Nadu Slum Clearance Board, Madurai Division has 39 projects on the TNRERA register since 2020 — 4,017 units/plots in total, concentrated in Central Chennai, Madurai District, Theni District. 0 completion-deadline extensions are recorded across their projects, and 29 projects are past their committed completion dates on the register. All figures from TNRERA public records.

39
2020
4,017
0

Builder Performance Dashboard

Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.

23%
0%
24
21 mo
2

Marked completed: share of their 39 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 29 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record.

All TNRERA registrations by The Executive Engineer, TNSCB, Madurai Division, T

ProjectRERA No.LocalityYearCommitted byUnits
Construction of 2 Blocks of Ground Floor + 3 Floors TN/20/Building/0047/2021 Madurai District 2021 31 May 2022
Construction of 2 Blocks of Ground Floor + 3 Floors TN/01/Building/0051/2021 Chengalpattu District 2021
Construction of Seven Blocks of Type–A: Block Nos. 1, 2, 5, 6, 7,… TN/01/Building/0053/2021 Porur Belt 2021
Construction of Slum tenements Additional Construction of 12 Blocks… TN/21/Building/0080/2021 Madurai District 2021 1,008 CANCELLED
Construction of Residential tenements Block-A & B of Ground Floor +… TN/07/Building/0082/2021 Salem District 2021 CANCELLED
Construction of Slum tenements of Block A1 to A8, Block B1 to B2: G… TN/21/Building/0098/2021 Theni District 2021 31 May 2025
Construction of 7 Blocks of A-A7 of Type-A: Ground Floor + 5 Floors TN/13/Building/0102/2021 Sriperumbudur–Oragadam 2021 31 May 2023
Construction of Block-A: Ground Floor + 4 Floors TN/08/Building/0103/2021 Namakkal District 2021 31 May 2023
Construction of Ground Floor + 4 Floors TN/29/Building/0115/2021 OMR Corridor 2021 31 Aug 2022
Construction of Ground Floor + 4 Floors TN/29/Building/0122/2021 OMR Corridor 2021 31 Aug 2022
Construction of Ground Floor + 3 Floors TN/29/Building/0123/2021 OMR Corridor 2021 31 Aug 2022
Construction of Slum Tenements of Ground Floor + 4 Floors TN/29/Building/0133/2021 OMR Corridor 2021 31 Aug 2022 20
Construction of Slum Tenements of Ground Floor + 4 Floors TN/29/Building/0134/2021 OMR Corridor 2021 31 Aug 2022 40
Construction of Stilt Floor + 11 Floors TN/29/Building/0195/2021 Central Chennai 2021 31 Dec 2022
Construction of 18 Blocks of Ground Floor + 2 Floors TN/11/Building/0230/2021 Theni District 2021 31 May 2024
Construction of Single EWS Block: Stilt Floor + 13 Floors TN/29/Building/0234/2021 Central Chennai 2021 30 Jun 2024 416
Construction of Residential Tenemental Blocks 1 to 7 - Ground Floor… TN/25/Building/0096/2020 Sivaganga District 2020 224 DONE
Construction of Twelve Blocks of Ground Floor + 3 Floors TN/25/Building/0100/2020 Sivaganga District 2020 DONE
Construction of Three Blocks of Type-A namely Block A1, A2, A3 with… TN/21/Building/0127/2020 Theni District 2020 DONE
Construction of Stilt Floor + 4 Floors TN/29/Building/0249/2020 Central Chennai 2020 31 Dec 2020 DONE
Construction of Block – A1 to A8 of Ground Floor + 3 Floors TN/20/Building/0250/2020 Madurai District 2020 4 Dec 2020 DONE
Appavoo Nagar & Subbu Pillai Thottam Phase-II TN/29/Building/0287/2020 Chennai District 2020 31 Mar 2021 48
Construction of Four Blocks of Block Nos. 1, 2, 3, 4 of Ground Floo… TN/20/Building/0304/2020 Madurai District 2020 DONE
Construction of Four Blocks of Type-A: Ground Floor + 3 Floors TN/20/Building/0305/2020 Madurai District 2020 31 Aug 2022
Manjalmedu TN/20/Building/0308/2020 Madurai District 2020 31 Oct 2022 320
Construction of Slum tenements with Ground Floor of Block A1 to A3,… TN/21/Building/0311/2020 Theni District 2020 31 Oct 2021 301
Construction of Eleven Blocks of Ground Floor + 3 Floors TN/21/Building/0317/2020 Theni District 2020
Construction of Stilt Floor + 4 Floors TN/29/Building/0322/2020 Central Chennai 2020 31 Dec 2020 DONE
Vazhaithoppu Phase-II TN/29/Building/0323/2020 Chennai District 2020 31 Mar 2021 204
Subedar Garden Scheme TN/29/Building/0329/2020 Central Chennai 2020 31 Aug 2022 300
Wallace Garden TN/29/Building/0342/2020 Central Chennai 2020 31 Jul 2021 128
Construction of Slum Tenements 3 Blocks of Stilt Floor + 5 Floors R… TN/29/Building/0343/2020 Central Chennai 2020 30 Jun 2021 80 DONE
Construction of Ground Floor + 5 Floors TN/29/Building/0346/2020 Central Chennai 2020 30 Jun 2021 DONE
Construction of Block – 1 of Ground Floor + 5 Floors TN/29/Building/0355/2020 Central Chennai 2020 31 Jul 2023
Construction of Phase – I, Type – A: Five Blocks of Ground Floo… TN/25/Building/0357/2020 Sivaganga District 2020 31 Dec 2023
Dr. Thomas Road Phase-I TN/29/Building/0362/2020 Central Chennai 2020 30 Apr 2024
Construction of Slum tenements of Typical Block A1 to A9, B1 to B7… TN/20/Building/0383/2020 Madurai District 2020 30 Jun 2024 808
Kuravargal Colony Phase-II TN/21/Building/0385/2020 Theni District 2020 120
Construction of Block-A1 to Block-A48 of Ground Floor + 3 Floors TN/20/Building/0412/2020 Madurai District 2020 31 Dec 2022

How to read this record

Does The Executive Engineer, TNSCB, Madurai Division, Tamil Nadu Slum Clearance Board, Madurai Division deliver on time?

No completion-deadline extensions are recorded across their 39 registered projects — a clean register on this measure.

Where does The Executive Engineer, TNSCB, Madurai Division, Tamil Nadu Slum Clearance Board, Madurai Division build?

Their registrations concentrate in Central Chennai, Madurai District, Theni District, OMR Corridor, Sivaganga District.