M/s. Green Valley Shelters (P) Ltd.
M/s. Green Valley Shelters (P) Ltd. has 7 projects on the TNRERA register since 2017 — 149 units/plots in total, concentrated in Coimbatore District, Ambattur–Avadi Belt, Porur Belt. 0 completion-deadline extensions are recorded across their projects, and 7 projects are past their committed completion dates on the register. All figures from TNRERA public records.
Builder Performance Dashboard
Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.
Marked completed: share of their 7 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 7 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record.
All TNRERA registrations by M/s. Green Valley Shelters (P) Ltd.
| Project | RERA No. | Locality | Year | Committed by | Units | |
|---|---|---|---|---|---|---|
| GVSPL Raajguru | TN/01/Building/008/2019 | OMR Corridor | 2019 | 15 Feb 2020 | 65 | |
| Construction of Stilt Floor + 4 Floors for the Flats FF – G1, SF… | TN/02/Building/0158/2019 | Ambattur–Avadi Belt | 2019 | 5 Mar 2020 | — | DONE |
| Construction of Stilt floor + 3 floors + 4th floor part | TN/02/Building/0296/2018 | Ambattur–Avadi Belt | 2018 | 1 Aug 2020 | 22 | |
| Green County – Block ‘C | TN/11/Building/0343/2018 | Coimbatore District | 2018 | 21 Jun 2021 | — | DONE |
| GVSPL Raksha | TN/02/Building/0352/2018 | Porur Belt | 2018 | 6 Aug 2020 | 34 | DONE |
| Construction of Block A – Stilt Floor+ 4 Floors | TN/11/Building/0202/2017 | Coimbatore District | 2017 | 21 Jun 2019 | 28 | DONE |
| Construction of Row Houses Block 1 to 24 with Ground Floor+ First F… | TN/11/Building/0203/2017 | Coimbatore District | 2017 | 21 Jun 2019 | — |
How to read this record
Does M/s. Green Valley Shelters (P) Ltd. deliver on time?
No completion-deadline extensions are recorded across their 7 registered projects — a clean register on this measure.
Where does M/s. Green Valley Shelters (P) Ltd. build?
Their registrations concentrate in Coimbatore District, Ambattur–Avadi Belt, Porur Belt, OMR Corridor.