M/s. Ruby Builders & Promoters has 29 projects on the TNRERA register since 2017 — 832 units/plots in total, concentrated in OMR Corridor, GST Road South, Chennai District. 0 completion-deadline extensions are recorded across their projects, and 13 projects are past their committed completion dates on the register. All figures from TNRERA public records.
29
2017
832
0
Builder Performance Dashboard
Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.
31%
0%
13
48 mo
100%
2.3 mo
Marked completed: share of their 29 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay.
Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%).
Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 17 with a known committed date.
Avg committed timeline: mean months between registration and committed completion, where both dates are on record.
Disclosure completeness: share of key filing fields (stage, building type, site extent, planning permission, units, completion date) present on the detailed register — sampled for 2 of 29 projects.Approval → RERA: median months between the planning-approval document date (OCR'd from the filed approval) and RERA registration, across 1 projects where both dates are readable.
All TNRERA registrations by M/s. Ruby Builders & Promoters