M/s. BSCPL Infrastructure Ltd.

M/s. BSCPL Infrastructure Ltd. has 7 projects on the TNRERA register since 2017 — 296 units/plots in total, concentrated in OMR Corridor, Chennai District. 0 completion-deadline extensions are recorded across their projects, and 7 projects are past their committed completion dates on the register. All figures from TNRERA public records.

7
2017
296
0

Builder Performance Dashboard

Computed from TNRERA register entries only — every metric's method is stated below it. Register status can lag reality; treat as one research input.

57%
0%
3
27 mo

Marked completed: share of their 7 registrations whose register status reads “Completed” (TN-wide: 81%) — note this naturally tracks portfolio age; a builder whose projects are mostly recent will show a low share without it meaning delay. Deadline extended: share with a recorded completion-date extension or “Extension given” status (TN-wide: 0%). Past date, not completed: projects whose RERA-committed date has passed without a “Completed” status, of 7 with a known committed date. Avg committed timeline: mean months between registration and committed completion, where both dates are on record.

All TNRERA registrations by M/s. BSCPL Infrastructure Ltd.

ProjectRERA No.LocalityYearCommitted byUnits
Violet TN/01/Building/016/2019 OMR Corridor 2019 31 Oct 2021 28 DONE
Indigo TN/01/Building/051/2019 OMR Corridor 2019 31 Dec 2021 36 DONE
Construction of Plot No.1A, 1B, 1C, 1D, 1E, 1F, 2A, 2B, 2C, 2D, 33… TN/01/Building/0084/2019 OMR Corridor 2019 31 Dec 2022
Conversion of public purpose Plot Nos. I & II lying in the approved layout No.PPD/LO No.04 TN/01/Layout/0077/2019 OMR Corridor 2019 31 Dec 2022
Project Details and Address TN/01/Building/0298/2018 Chennai District 2018 31 Oct 2019
Construction of Stilt Floor+ 4 Floors TN/01/Building/0183/2017 OMR Corridor 2017 31 Dec 2018 168 DONE
Construction of Block A – Basement Floor+ Ground Floor+ 3 Floors… TN/01/Building/0191/2017 OMR Corridor 2017 1 Jul 2018 64 DONE

How to read this record

Does M/s. BSCPL Infrastructure Ltd. deliver on time?

No completion-deadline extensions are recorded across their 7 registered projects — a clean register on this measure.

Where does M/s. BSCPL Infrastructure Ltd. build?

Their registrations concentrate in OMR Corridor, Chennai District.