VerifyRERAAndhra Pradesh · AP-RERA
Home/Andhra Pradesh/Guntur/Suvarnakuteer Phase 3

Suvarnakuteer Phase 3

P07140060478 PAST DUE 5.4 yrs past committed date

Yes — P07140060478, registered 9 Sep 2019 with AP-RERA, with a committed completion date of 7 Mar 2021. It is currently 5.4 years past that date.

C
50%
7 Mar 2021
Yes

Health score components

ComponentScoreReading
Timeline adherence12Overdue 5.4 yrs vs the date committed at registration
Construction progress50Promoter reports 50% of development complete.
Registration documents100Registration certificate is on file with AP-RERA.
Legal cleanliness100No litigation flagged on the AP-RERA record.
Builder track record45Based on Suvarnakuteer Developers Private Limited's portfolio: past-due share and litigation across their AP-RERA projects.

Confidence: full. Andhra Pradesh does not publish sold-unit counts, and publishes a progress % only for projects reporting ongoing status, so missing components are excluded and the rest reweighted. Derived from public AP-RERA records as of 2026-07-25.

Registration record

FieldValue
BuilderSuvarnakuteer Developers Private Limited
TypePlotted · plots
LocationBALUSUPADU, Pedakurapadu, Guntur
Registered on9 Sep 2019
Committed completion7 Mar 2021
Reported progress50% complete
Registration certificateOn file with AP-RERA
LitigationNone flagged
Official recordVerify on the AP-RERA portal

Is Suvarnakuteer Phase 3 RERA registered in Andhra Pradesh?

Yes — P07140060478, registered 9 Sep 2019 with AP-RERA, with a committed completion date of 7 Mar 2021. It is currently 5.4 years past that date.

Who is the builder of Suvarnakuteer Phase 3?

Suvarnakuteer Developers Private Limited. See their full Andhra Pradesh track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.