P06180024662 PAST DUE 0.6 yrs past committed date

Yes — P06180024662, registered 4 Apr 2024 with AP-RERA, with a committed completion date of 14 Dec 2025. It is currently 0.6 years past that date.

C
14 Dec 2025

Health score components

ComponentScoreReading
Timeline adherence49Overdue 0.6 yrs vs the date committed at registration
Construction progressn/aNo progress % published (AP publishes this only for projects reporting ongoing status).
Registration documents45No registration certificate document was found on the AP-RERA record.
Legal cleanliness100No litigation flagged on the AP-RERA record.
Builder track record45Based on Sunkara Durgarani's portfolio: past-due share and litigation across their AP-RERA projects.

Confidence: partial. Andhra Pradesh does not publish sold-unit counts, and publishes a progress % only for projects reporting ongoing status, so missing components are excluded and the rest reweighted. Derived from public AP-RERA records as of 2026-07-24.

Registration record

FieldValue
BuilderSunkara Durgarani
TypeResidential · apartment
LocationKANURU (U), Penamaluru, Krishna
Registered on4 Apr 2024
Committed completion14 Dec 2025
Reported progressnot published
Registration certificateNot found on record
LitigationNone flagged
Official recordVerify on the AP-RERA portal

Is Sri Lakshmi Enclave RERA registered in Andhra Pradesh?

Yes — P06180024662, registered 4 Apr 2024 with AP-RERA, with a committed completion date of 14 Dec 2025. It is currently 0.6 years past that date.

Who is the builder of Sri Lakshmi Enclave?

Sunkara Durgarani. See their full Andhra Pradesh track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.