P03240231422 PAST DUE 3.6 yrs past committed date

Yes — P03240231422, registered 10 Feb 2021 with AP-RERA, with a committed completion date of 23 Dec 2022. It is currently 3.6 years past that date.

C
90%
23 Dec 2022
Yes

Health score components

ComponentScoreReading
Timeline adherence12Overdue 3.6 yrs vs the date committed at registration
Construction progress90Promoter reports 90% of development complete.
Registration documents100Registration certificate is on file with AP-RERA.
Legal cleanliness100No litigation flagged on the AP-RERA record.
Builder track record45Based on Sri Hari Constructions's portfolio: past-due share and litigation across their AP-RERA projects.

Confidence: full. Andhra Pradesh does not publish sold-unit counts, and publishes a progress % only for projects reporting ongoing status, so missing components are excluded and the rest reweighted. Derived from public AP-RERA records as of 2026-07-24.

Registration record

FieldValue
BuilderSri Hari Constructions
TypeResidential · apartment
LocationVepagunta, Pendurthi, Visakhapatnam
Registered on10 Feb 2021
Committed completion23 Dec 2022
Reported progress90% complete
Registration certificateOn file with AP-RERA
LitigationNone flagged
Official recordVerify on the AP-RERA portal

Is Simhadri Towers RERA registered in Andhra Pradesh?

Yes — P03240231422, registered 10 Feb 2021 with AP-RERA, with a committed completion date of 23 Dec 2022. It is currently 3.6 years past that date.

Who is the builder of Simhadri Towers?

Sri Hari Constructions. See their full Andhra Pradesh track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.