P13070702778 PAST DUE 1.7 yrs past committed date

Yes — P13070702778, registered 27 Jul 2022 with AP-RERA, with a committed completion date of 28 Oct 2024. It is currently 1.7 years past that date.

D
28 Oct 2024

Health score components

ComponentScoreReading
Timeline adherence29Overdue 1.7 yrs vs the date committed at registration
Construction progressn/aNo progress % published (AP publishes this only for projects reporting ongoing status).
Registration documents45No registration certificate document was found on the AP-RERA record.
Legal cleanliness100No litigation flagged on the AP-RERA record.
Builder track record45Based on Guntakanti Mallareddy's portfolio: past-due share and litigation across their AP-RERA projects.

Confidence: partial. Andhra Pradesh does not publish sold-unit counts, and publishes a progress % only for projects reporting ongoing status, so missing components are excluded and the rest reweighted. Derived from public AP-RERA records as of 2026-07-25.

Registration record

FieldValue
BuilderGuntakanti Mallareddy
TypeResidential · apartment
LocationWARDNO-45, Kurnool, Kurnool
Registered on27 Jul 2022
Committed completion28 Oct 2024
Reported progressnot published
Registration certificateNot found on record
LitigationNone flagged
Official recordVerify on the AP-RERA portal

Is Silver Oak 3 A Block RERA registered in Andhra Pradesh?

Yes — P13070702778, registered 27 Jul 2022 with AP-RERA, with a committed completion date of 28 Oct 2024. It is currently 1.7 years past that date.

Who is the builder of Silver Oak 3 A Block?

Guntakanti Mallareddy. See their full Andhra Pradesh track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.