P03280034018 PAST DUE 1.3 yrs past committed date

Yes — P03280034018, registered 13 Sep 2023 with AP-RERA, with a committed completion date of 23 Mar 2025. It is currently 1.3 years past that date.

D
1%
23 Mar 2025
Yes

Health score components

ComponentScoreReading
Timeline adherence36Overdue 1.3 yrs vs the date committed at registration
Construction progress1Promoter reports 1% of development complete.
Registration documents100Registration certificate is on file with AP-RERA.
Legal cleanliness100No litigation flagged on the AP-RERA record.
Builder track record45Based on Sri Balaji Infra Developers's portfolio: past-due share and litigation across their AP-RERA projects.

Confidence: full. Andhra Pradesh does not publish sold-unit counts, and publishes a progress % only for projects reporting ongoing status, so missing components are excluded and the rest reweighted. Derived from public AP-RERA records as of 2026-07-25.

Registration record

FieldValue
BuilderSri Balaji Infra Developers
TypeResidential · apartment
LocationMadhuravada (u), Visakhapatnam, Visakhapatnam
Registered on13 Sep 2023
Committed completion23 Mar 2025
Reported progress1% complete
Registration certificateOn file with AP-RERA
LitigationNone flagged
Official recordVerify on the AP-RERA portal

Is Sai Viswanath Residency RERA registered in Andhra Pradesh?

Yes — P03280034018, registered 13 Sep 2023 with AP-RERA, with a committed completion date of 23 Mar 2025. It is currently 1.3 years past that date.

Who is the builder of Sai Viswanath Residency?

Sri Balaji Infra Developers. See their full Andhra Pradesh track record on this site.

Shortlisting here? Verify before you pay.