Health City Phase-2
P02280155065 STALLED 2.9 yrs past committed date
Yes — P02280155065, registered 18 Oct 2024 with AP-RERA, with a committed completion date of 26 Aug 2023. It is currently 2.9 years past that date.
Health score components
| Component | Score | Reading |
|---|---|---|
| Timeline adherence | 16 | New/registered project years past its committed date with no reported progress. |
| Construction progress | n/a | No progress % published (AP publishes this only for projects reporting ongoing status). |
| Registration documents | 100 | Registration certificate is on file with AP-RERA. |
| Legal cleanliness | 100 | No litigation flagged on the AP-RERA record. |
| Builder track record | 45 | Based on Sri Bhagavan Builders Pvt Ltd's portfolio: past-due share and litigation across their AP-RERA projects. |
Confidence: partial. Andhra Pradesh does not publish sold-unit counts, and publishes a progress % only for projects reporting ongoing status, so missing components are excluded and the rest reweighted. Derived from public AP-RERA records as of 2026-07-25.
Registration record
| Field | Value |
|---|---|
| Builder | Sri Bhagavan Builders Pvt Ltd |
| Type | Plotted · plots |
| Location | VIZIANAGARAM BIT-II, Vizianagaram, Vizianagaram |
| Registered on | 18 Oct 2024 |
| Committed completion | 26 Aug 2023 |
| Reported progress | not published |
| Registration certificate | On file with AP-RERA |
| Litigation | None flagged |
| Official record | Verify on the AP-RERA portal |
Is Health City Phase-2 RERA registered in Andhra Pradesh?
Yes — P02280155065, registered 18 Oct 2024 with AP-RERA, with a committed completion date of 26 Aug 2023. It is currently 2.9 years past that date.
Who is the builder of Health City Phase-2?
Sri Bhagavan Builders Pvt Ltd. See their full Andhra Pradesh track record on this site.