P03310011143 PAST DUE 2.9 yrs past committed date

Yes — P03310011143, registered 8 Oct 2020 with AP-RERA, with a committed completion date of 27 Aug 2023. It is currently 2.9 years past that date.

D
45%
27 Aug 2023

Health score components

ComponentScoreReading
Timeline adherence12Overdue 2.9 yrs vs the date committed at registration
Construction progress45Promoter reports 45% of development complete.
Registration documents45No registration certificate document was found on the AP-RERA record.
Legal cleanliness100No litigation flagged on the AP-RERA record.
Builder track record45Based on Srinivasa Rao Niddavolu's portfolio: past-due share and litigation across their AP-RERA projects.

Confidence: full. Andhra Pradesh does not publish sold-unit counts, and publishes a progress % only for projects reporting ongoing status, so missing components are excluded and the rest reweighted. Derived from public AP-RERA records as of 2026-07-26.

Registration record

FieldValue
BuilderSrinivasa Rao Niddavolu
TypeResidential · apartment
LocationPedagantyada (U), Pedagantyada, Visakhapatnam
Registered on8 Oct 2020
Committed completion27 Aug 2023
Reported progress45% complete
Registration certificateNot found on record
LitigationNone flagged
Official recordVerify on the AP-RERA portal

Is Harika Enclave RERA registered in Andhra Pradesh?

Yes — P03310011143, registered 8 Oct 2020 with AP-RERA, with a committed completion date of 27 Aug 2023. It is currently 2.9 years past that date.

Who is the builder of Harika Enclave?

Srinivasa Rao Niddavolu. See their full Andhra Pradesh track record on this site.

Shortlisting here? Verify before you pay.

We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.