Vaisakhi Developers
Vaisakhi Developers has 5 AP-RERA registered projects across Visakhapatnam. 3 are past their committed completion date and 0 are reported complete.
5
3
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Vaisakhi Pearl | Visakhapatnam | 3 Feb 2021 | 27 Jul 2023 | STALLED | C |
| Vaisakhi Skypark Block 1,2,3,4,7 | Visakhapatnam | 18 Jun 2019 | 11 Mar 2025 | PAST DUE | C |
| Vaisakhi Prime | Visakhapatnam | 27 Jul 2023 | 10 Oct 2025 | PAST DUE | B |
| Vaisakhi Sundar Sky Lounge | Visakhapatnam | 13 Sep 2023 | 1 Aug 2029 | REGISTERED | A |
| Vaisakhi Skypark 5,6,8 | Visakhapatnam | 3 Feb 2021 | 4 Dec 2026 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Vaisakhi Developers have in Andhra Pradesh?
Vaisakhi Developers has 5 AP-RERA registered projects across Visakhapatnam. 3 are past their committed completion date and 0 are reported complete.
Does Vaisakhi Developers have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.