Stbl Projects Ltd & Others
Stbl Projects Ltd & Others has 10 AP-RERA registered projects across Visakhapatnam, Krishna. 8 are past their committed completion date and 0 are reported complete.
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Lakshmi Venkateswara Gardens- Extension | Krishna | 17 Sep 2019 | 16 Dec 2019 | PAST DUE | C |
| Sita Rama Gardens Phase 4 | Visakhapatnam | 6 May 2019 | 18 May 2021 | STALLED | C |
| Lakshmi Madhusudana Gardens Extension Phase 2 | Krishna | 6 Jan 2020 | 1 Mar 2022 | STALLED | C |
| Sri Krishna Green Villas | Visakhapatnam | 28 Feb 2020 | 24 Aug 2022 | STALLED | C |
| Sita Rama Gardens Phase 6 | Visakhapatnam | 9 Oct 2020 | 22 Oct 2022 | STALLED | C |
| Stbl’s Vasudha Gardens | Krishna | 13 Aug 2022 | 3 Jun 2024 | STALLED | C |
| Sita Rama Gardens Phase – 6 Extension | Visakhapatnam | 31 Dec 2021 | 14 Sep 2024 | PAST DUE | C |
| Vasudha -1 | Krishna | 26 May 2023 | 17 Nov 2025 | PAST DUE | B |
| Sridevi Gardens Phase Ii | Visakhapatnam | 28 Aug 2024 | 15 Mar 2027 | REGISTERED | A |
| Sri Krishna Green Villas Phase -Ii | Visakhapatnam | 9 May 2024 | 12 Jan 2027 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Stbl Projects Ltd & Others have in Andhra Pradesh?
Stbl Projects Ltd & Others has 10 AP-RERA registered projects across Visakhapatnam, Krishna. 8 are past their committed completion date and 0 are reported complete.
Does Stbl Projects Ltd & Others have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.