Sri Vijaya Sai Constructions
Sri Vijaya Sai Constructions has 3 AP-RERA registered projects across Guntur. 1 are past their committed completion date and 0 are reported complete.
3
1
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Meenakshi Residency | Guntur | 28 Mar 2020 | 30 Jun 2022 | STALLED | C |
| Aparna Residency | Guntur | 29 Sep 2025 | 12 Jun 2028 | REGISTERED | A |
| Vaishnavi Residency | Guntur | 11 Jun 2025 | 7 Dec 2027 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Sri Vijaya Sai Constructions have in Andhra Pradesh?
Sri Vijaya Sai Constructions has 3 AP-RERA registered projects across Guntur. 1 are past their committed completion date and 0 are reported complete.
Does Sri Vijaya Sai Constructions have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.
Shortlisting here? Verify before you pay.
We check title and RERA standing, benchmark the price against registration data, and negotiate with the builder on your side. Free first consultation.