Sri Sai Infra Developers Private Limited
Sri Sai Infra Developers Private Limited has 4 AP-RERA registered projects across East Godavari, Visakhapatnam. 3 are past their committed completion date and 0 are reported complete.
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Sri Aashirwad | East Godavari | 31 May 2019 | 11 Sep 2021 | STALLED | C |
| Sree Aanjaneyam | East Godavari | 7 Jun 2022 | 12 Apr 2025 | PAST DUE | C |
| Swarna Residency | Visakhapatnam | 13 Sep 2023 | 1 Jul 2025 | PAST DUE | B |
| Amrutha Residency | Visakhapatnam | 28 Aug 2024 | 11 Apr 2027 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Sri Sai Infra Developers Private Limited have in Andhra Pradesh?
Sri Sai Infra Developers Private Limited has 4 AP-RERA registered projects across East Godavari, Visakhapatnam. 3 are past their committed completion date and 0 are reported complete.
Does Sri Sai Infra Developers Private Limited have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.