Sri Sai Builders And Developers
Sri Sai Builders And Developers has 3 AP-RERA registered projects across East Godavari. 3 are past their committed completion date and 0 are reported complete.
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Sri Sai Jaguruthi Residency | East Godavari | 25 Dec 2018 | 4 Apr 2021 | PAST DUE | D |
| Sri Sai Venkateswara Grand | East Godavari | 13 May 2021 | 29 May 2023 | STALLED | C |
| Sri Sai Square | East Godavari | 2 Dec 2021 | 20 Jul 2024 | STALLED | C |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Sri Sai Builders And Developers have in Andhra Pradesh?
Sri Sai Builders And Developers has 3 AP-RERA registered projects across East Godavari. 3 are past their committed completion date and 0 are reported complete.
Does Sri Sai Builders And Developers have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.