Sri Lakshmi Builders
Sri Lakshmi Builders has 7 AP-RERA registered projects across West Godavari, Guntur, East Godavari. 4 are past their committed completion date and 0 are reported complete.
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Sri Ram Krishna Sai Appartments | West Godavari | 13 Feb 2020 | 27 Aug 2022 | STALLED | C |
| Sri Anjaneya Enclave | Guntur | 28 May 2021 | 15 Jan 2024 | STALLED | C |
| Sri Sabitha Towers | West Godavari | 10 Dec 2022 | 2 Nov 2024 | PAST DUE | C |
| Sri Anjaneyam Heights | Guntur | 3 Sep 2022 | 17 Jul 2025 | PAST DUE | B |
| Sri Lakshmi Enclaves | West Godavari | 19 Sep 2025 | 9 Aug 2028 | REGISTERED | A |
| Sri Lakshmi Heights | East Godavari | 5 Jun 2025 | 17 Oct 2027 | REGISTERED | A |
| Sri Lakshmi Arcade | Guntur | 9 Dec 2024 | 17 Dec 2026 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Sri Lakshmi Builders have in Andhra Pradesh?
Sri Lakshmi Builders has 7 AP-RERA registered projects across West Godavari, Guntur, East Godavari. 4 are past their committed completion date and 0 are reported complete.
Does Sri Lakshmi Builders have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.