Sri Gayathri Housing
Sri Gayathri Housing has 3 AP-RERA registered projects across Guntur. 3 are past their committed completion date and 0 are reported complete.
3
3
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Jayam Residency | Guntur | 18 Mar 2020 | 28 Dec 2022 | STALLED | C |
| Sri Vatsa Residency | Guntur | 9 Jan 2022 | 15 Sep 2024 | PAST DUE | C |
| Harshitha Homes | Guntur | 9 Jan 2022 | 12 Oct 2024 | PAST DUE | C |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Sri Gayathri Housing have in Andhra Pradesh?
Sri Gayathri Housing has 3 AP-RERA registered projects across Guntur. 3 are past their committed completion date and 0 are reported complete.
Does Sri Gayathri Housing have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.