Skandhanshi Infra Projects India Pvt Ltd has 34 AP-RERA registered projects across Ananthapuramu, Kurnool, Y.S.R Kadapa. 31 are past their committed completion date and 0 are reported complete.

34
31
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Sarovar Ananthapuramu 15 Sep 2020 31 Jul 2021 PAST DUE C
Golden Tulip Kurnool 15 Sep 2020 24 Nov 2021 PAST DUE C
Skandhanshi Vyapaar Kurnool 23 Oct 2020 28 Feb 2022 PAST DUE C
Skandhanshi Park Avanue Kurnool 23 Oct 2020 29 Apr 2022 PAST DUE C
Skandhanshi Kalpataru Ananthapuramu 11 Sep 2020 25 May 2022 PAST DUE C
Hill Crest Kurnool 15 Sep 2020 23 Oct 2022 PAST DUE C
Skandhanshi Towers Kurnool 23 Oct 2020 7 Jan 2023 PAST DUE C
Skandhanshi Sree Aishwaryam Kurnool 23 Oct 2020 13 Apr 2023 STALLED C
Pudami Estates Ananthapuramu 11 Sep 2020 13 Apr 2023 PAST DUE C
Skandhanshi Aavirbhav Y.S.R Kadapa 23 Oct 2020 3 Jul 2023 STALLED C
Skandhanshi Shops & Spaces Kurnool 1 Jul 2021 10 Aug 2023 STALLED C
Skandhanshi Rambo Platina Block-A Ananthapuramu 1 Jul 2021 27 Aug 2023 STALLED C
Skandhanshi Hibiscus Kurnool 31 Dec 2021 5 Oct 2023 STALLED C
Skandhanshi Rambo Platina Block B Ananthapuramu 1 Jul 2021 30 Sep 2023 STALLED C
Skandhanshi Aakruthi Kurnool 22 Jan 2021 21 Oct 2023 STALLED C
Skandhanshi Gokulam Kurnool 13 Aug 2021 5 Feb 2024 STALLED C
Skandhanshi Gardenia Kurnool 28 Mar 2023 23 May 2024 STALLED C
Skandhanshi Daffodils Kurnool 1 Jul 2021 18 May 2024 STALLED C
Skandhanshi Aakruhti B Block Kurnool 26 May 2023 24 Jul 2024 PAST DUE C
Skandhanshi Silver Nest Kurnool 29 Mar 2022 11 Oct 2024 PAST DUE C
Skandhanhsi Mannath Block B Kurnool 29 Mar 2022 7 Oct 2024 PAST DUE C
Skandhanshi Mannath Block A Kurnool 9 Jan 2022 12 Nov 2024 PAST DUE C
Skandhanshi Divi Kurnool 26 May 2023 23 Mar 2025 PAST DUE C
Skandhanshi Prithvi Kurnool 13 Sep 2023 5 Apr 2025 PAST DUE C
Skandhanshi K R Residency Ananthapuramu 29 Mar 2022 23 Apr 2025 PAST DUE C
Skandhanshi Nanda Gokulam Kurnool 3 Sep 2022 30 Apr 2025 PAST DUE C
Skandhanshi Dharani Kurnool 26 May 2023 20 Jun 2025 PAST DUE C
Skandhanshi Aavirbhav Phase Ii Y.S.R Kadapa 28 Mar 2023 24 Jul 2025 PAST DUE C
Skandhanshi Garden Vista Ananthapuramu 18 Nov 2023 19 Oct 2025 PAST DUE B
Skandhanshi Green Acres Kurnool 18 Nov 2023 8 Jan 2026 PAST DUE B
Skandhanshi Dharani Extension Kurnool 14 Aug 2023 13 Jun 2026 PAST DUE B
Skandhanshi Jampala Hynesta Kurnool 27 May 2024 19 Feb 2030 REGISTERED A
Skandhanshi Anandalahari Ananthapuramu 13 Sep 2023 13 Sep 2030 REGISTERED A
Skandhanshi Cloud 9 Kurnool 1 Jul 2021 5 Oct 2026 DUE SOON B

Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.

How many RERA projects does Skandhanshi Infra Projects India Pvt Ltd have in Andhra Pradesh?

Skandhanshi Infra Projects India Pvt Ltd has 34 AP-RERA registered projects across Ananthapuramu, Kurnool, Y.S.R Kadapa. 31 are past their committed completion date and 0 are reported complete.

Does Skandhanshi Infra Projects India Pvt Ltd have any RERA litigation in Andhra Pradesh?

No litigation is flagged on the AP-RERA record for their projects.