Sivashakthi Townships
Sivashakthi Townships has 7 AP-RERA registered projects across Visakhapatnam. 7 are past their committed completion date and 0 are reported complete.
7
7
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Highway City (Phase-1) | Visakhapatnam | 13 Feb 2020 | 30 May 2020 | STALLED | C |
| Highway City | Visakhapatnam | 23 Apr 2019 | 7 Jul 2021 | STALLED | C |
| Highway City Phase-3 | Visakhapatnam | 5 Aug 2019 | 28 Jan 2022 | STALLED | C |
| Highway City Phase 4 | Visakhapatnam | 15 Apr 2020 | 2 Dec 2022 | STALLED | C |
| Highway City Phase-3 Extension | Visakhapatnam | 19 Mar 2020 | 2 Dec 2022 | STALLED | C |
| Highway City Phase Ii Extension | Visakhapatnam | 23 Sep 2021 | 24 Feb 2024 | STALLED | C |
| Highway City Phase-5 | Visakhapatnam | 23 Sep 2021 | 25 Mar 2024 | STALLED | C |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Sivashakthi Townships have in Andhra Pradesh?
Sivashakthi Townships has 7 AP-RERA registered projects across Visakhapatnam. 7 are past their committed completion date and 0 are reported complete.
Does Sivashakthi Townships have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.