Royalmindz Estates Pvt Ltd
Royalmindz Estates Pvt Ltd has 3 AP-RERA registered projects across Vizianagaram. 2 are past their committed completion date and 0 are reported complete.
3
2
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Royal City Phase Iv | Vizianagaram | 23 Oct 2020 | 27 Apr 2021 | PAST DUE | C |
| Royal City Phase V | Vizianagaram | 5 Mar 2025 | 15 Apr 2026 | PAST DUE | B |
| Royal City Phase Vi | Vizianagaram | 20 Mar 2025 | 4 Nov 2026 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-25. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Royalmindz Estates Pvt Ltd have in Andhra Pradesh?
Royalmindz Estates Pvt Ltd has 3 AP-RERA registered projects across Vizianagaram. 2 are past their committed completion date and 0 are reported complete.
Does Royalmindz Estates Pvt Ltd have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.