Rekha Constructions
Rekha Constructions has 2 AP-RERA registered projects across Guntur. 1 are past their committed completion date and 0 are reported complete.
2
1
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| Space Gardens | Guntur | 20 Jan 2025 | 17 May 2026 | PAST DUE | B |
| Vijaya Grands | Guntur | 7 Nov 2025 | 25 May 2028 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does Rekha Constructions have in Andhra Pradesh?
Rekha Constructions has 2 AP-RERA registered projects across Guntur. 1 are past their committed completion date and 0 are reported complete.
Does Rekha Constructions have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.