Naidu Constructions

Naidu Constructions has 3 AP-RERA registered projects across Visakhapatnam. 1 are past their committed completion date and 0 are reported complete.

3
1
0
0

Registered projects

ProjectDistrictRegisteredCommitted dateStatusBand
Naidu's Towers Visakhapatnam 9 Jul 2022 13 Jan 2025 PAST DUE B
Naidu's Nanda Gokul Residency Visakhapatnam 21 Aug 2025 17 Jul 2028 REGISTERED A
Naidu's Adiraju Enclave Visakhapatnam 11 Jun 2025 3 May 2028 REGISTERED A

Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.

How many RERA projects does Naidu Constructions have in Andhra Pradesh?

Naidu Constructions has 3 AP-RERA registered projects across Visakhapatnam. 1 are past their committed completion date and 0 are reported complete.

Does Naidu Constructions have any RERA litigation in Andhra Pradesh?

No litigation is flagged on the AP-RERA record for their projects.