M N Builders
M N Builders has 5 AP-RERA registered projects across East Godavari. 3 are past their committed completion date and 0 are reported complete.
5
3
0
0
Registered projects
| Project | District | Registered | Committed date | Status | Band |
|---|---|---|---|---|---|
| M N Venkatadri Heights | East Godavari | 7 Nov 2019 | 17 May 2020 | PAST DUE | C |
| M N Amrutha Homes | East Godavari | 8 Dec 2020 | 24 Feb 2023 | STALLED | C |
| M N Panangipalli Residency | East Godavari | 9 May 2023 | 22 Dec 2025 | PAST DUE | B |
| M N Square | East Godavari | 20 Jan 2025 | 12 Sep 2027 | REGISTERED | A |
| M N Abhi Greens | East Godavari | 19 Feb 2024 | 23 Jan 2027 | REGISTERED | A |
Track record derived from public AP-RERA records as of 2026-07-24. "Past due" = past the completion date committed at registration without being reported complete; Andhra Pradesh does not publish granted-extension counts.
How many RERA projects does M N Builders have in Andhra Pradesh?
M N Builders has 5 AP-RERA registered projects across East Godavari. 3 are past their committed completion date and 0 are reported complete.
Does M N Builders have any RERA litigation in Andhra Pradesh?
No litigation is flagged on the AP-RERA record for their projects.